ROAD CONSTRUCTION

GARFIELD TOWNSHIP - 440TH AVE RECONSTRUCTION

23,000 CY of excavation and over 21,000 tons of gravel surfacing placed, along with installation of new RCP culverts.

Contract Amount:   $1,209,966.04

Completed:             12/15/2020

Engineer:                 Civil Design, Brookings, SD

CLARK COUNTY HIGHWAY 38 RECONSTRUCTION

Removal of existing asphalt surfacing; importing 7,500 tons of base course; spreading, mixing, grading, and compacting 760 ton of cement treated subgrade; and laying almost 4,000 ton of new asphalt surfacing.

Contract Amount:   $1,283,924.82

Completed:             8/14/2024

Engineer:                 IMEG Corp, Sioux Falls, SD