HEAVY EXCAVATION
ASTORIA WASTEWATER SYSTEM IMPROVEMENTS
Reconstruction of wastewater lagoon, and installation of new lift station.
Contract Amount: $367,326.50
Completed: 1/19/2018
Engineer: SPN & Associates, Mitchell, SD
RIVERVIEW, LLP - GARFIELD DAIRY
Over 750,000 CY of excavation that included retention basins, a large holding barn, milk parlor, feed pad and more.
Contract Amount: $7,724,831.71
Completed: 12/17/2020
Engineer: Settje Agri-Services & Engineering, Raymond, NE
AGROPUR CHEESE PLANT EXPANSION
Installation of site utilities, mass excavation, building excavation, parking lots, and general site preparation
Contract Amount: $2,303,218.93
Completed: 6/19/2019
Engineer: E.A. Bonelli & Assoc. along with ISG
Prime Contractor: Miron Construction
RIVERVIEW, LLP - WASHINGTON DAIRY
Over 750,000 CY of excavation that included retention basins, a large holding barn, milk parlor, feed pad and more.
Contract Amount: $7,277,034.36
Completed: 2/28/2023
Engineer: Settje Agri-Services & Engineering, Raymond, NE